TIMESCHEDULE OF PROJECT
ACTIVITY | DURATION (in days) |
START
|
FINISH
|
|
29.
|
Cellular Blocks (Caisson) |
675
|
09/04/95
|
04/03/98
|
30.
|
Vibro-compacted method |
95
|
09/04/95
|
01/12/96
|
31.
|
Geotechnical works - Confirmation of vibro-compacted method |
90
|
09/18/95
|
01/19/96
|
32.
|
Construction of the first caisson |
60
|
10/19/95
|
01/10/96
|
33.
|
Excavation of sea bottom (caisson area) |
240
|
09/25/95
|
08/23/96
|
34.
|
Base riprap |
240
|
10/02/95
|
08/30/96
|
35.
|
Construction of 22 caisson |
250
|
01/25/96
|
01/08/97
|
36.
|
Construction of 24 caisson |
260
|
01/09/97
|
01/07/98
|
37.
|
Transport -Anchor-Casting |
500
|
03/21/96
|
02/18/98
|
38.
|
Construction of relieving prism (caisson) |
500
|
03/28/96
|
02/25/98
|
39.
|
Construction of filter (caisson) |
500
|
04/01/96
|
02/27/98
|
40.
|
Paving of cellular boxes |
500
|
04/04/96
|
03/04/98
|
41.
|
Completion of superstructures landfills |
200
|
06/02/97
|
03/06/98
|
42.
|
Superstructure construction |
200
|
06/23/97
|
03/27/98
|
43.
|
Superstructure equipment |
200
|
06/30/97
|
04/03/98
|
44.
|
Covering of cellular boxes |
50
|
04/06/98
|
06/12/98
|
45.
|
Architectural modulation |
30
|
05/11/98
|
06/19/98
|
46.
|
Construction of roads |
30
|
05/11/98
|
06/19/98
|
47.
|
Remaining works |
60
|
04/06/98
|
06/26/98
|
48.
|
Road Asphalting |
25
|
05/25/98
|
06/26/98
|
49.
|
End of works |
1
|
06/29/98
|
06/29/98
|