A. Port construction | ||
Excavations and Landfills: | 267.215.000 GRD | |
Quay Walls: | 1.185.689.500 GRD | |
Reinforced Concrete Works: | 1.598.505.000 GRD | |
Projects for the improvement of the foundation ground: | 142.500.000 GRD | |
Architectural formations of superstructure: | 41.204.500 GRD | |
|
||
Total: | 3.235.114.000 GRD | |
B. Technical Studies: | 323.342.436 GRD | |
C. Geotechnical Study: | 8.348.158 GRD | |
Total Cost of Works: | 3.566.804.594 GRD | |
General Expenses and Contractor Profit: | 640.024.827 GRD | |
Unexpected Expenses: | 73.277.156 GRD | |
Review: | 142.672.184 GRD | |
VAT: | 575.221.239 GRD | |
|
||
Total project cost: | 5.000.000.000 GRD |
Note: 340.75 GRD = 1 €