The optimum
economic and technical solution regarding the number of berths was the
following:
- 3 available independent functional berths for simultaneous
stern-moored car ferries
- 2 available independent functional berths for simultaneous
side-moored cruise ships
- Prediction for at least one additional stern-moored
car ferry, in addition to two side-moored cruise ships
The final design of the project (7 ramps are scheduled
altogether) allows for the simultaneous
use of the available quay walls by 4
or possibly 5 car ferries.
|