Introduction | Excavations | Cross Section | Construction | Concrete Construction | Other Issues | Transport-Installation | Gravel Filling | Quay Walls | Equipment Performance
 

GRAVEL FILLING

Gravel filling of Cellular Box Caissons

The study provided for the gravel filling of the back caisson cells.  

The construction company argued that gravel filling of the back cells only would result in:

  1. Differential settlements and inward turn of the caissons.
  2. Non-observance of the alignment.
  3. Problems in the construction of superstructures and installation of bumpers due to the non-observance of the alignment.

The solution proposed by the contractor was the simultaneous gravel filling of all caisson cells; however, it was not accepted due to cost concerns. The result was undesirable. Deflections from the alignment of the front were on the order of 30 cm.

Caisson landslides

The construction company had underlined the risk of increase of the reflection factor, which would lead to the increase of the hydrodynamic pressures on the caissons.
The supervising office of the Ministry of Public Works followed consultant and insisted on the initial foundation level at -11.00 m. The answer to the problem was given by the absorbent front, which provided, initially in the studt, a reflection factor equal to 0.35. The modified absorbent front with the addition of 2 additional rows of holes, combined with the internal holes (as presented in the hydraulic study) the 0.60 m settlement led to a reflection factor of 0.40, a value that was initially provided by the initial study.

   

Next Page

Technical studies

Project construction

Financial data