CONSTRUCTION - CONCRETE FOUNDATION
OF CELLULAR BOX CAISSONS

The study did not provided for methods or locations for the construction of caissons. Initially, it was considered possible to construct them on a dry dock platform on the island. However, a number of environmental reasons did not allow this mode of construction. Thus, the construction company sought one mode of construction with the least intervention on the land area of the island.
The solution was given by a combination of a floating and submerging, 800-tonnes platform, that was leased by the Italian company "Grandi Lavori Fincosit".

Zoom
Floating submerging platform
Zoom
Docking of platform

   