EQUIPMENT PERFORMANCE

Caisson Foundation Prism

  • Construction Period: 15 months
  • Monthly average: 18,000 m^3
  • Mean daily output: 752 m^3.
Loading was performed in a quarry area, at 10 km distance from the construction site, with a CAT 245 hoe. The materials were transferred to the worksite by 15 trucks, 15-m^3 carrier capacities.
(It is noted that the weather-side foundation led to 25% reduction of the average).

   