QUAY-WALL SUPERSTRUCTURES AT THE FRONT
OF THE ARTIFICIAL ISLAND

Superstructure Equipment

The scheduled equipment of the caisson superstructures is shown in the following table.

Caisson
Location of the Scheduled Equipment

Á1-Á9

Casted-steel mooring bollards, 50-tonnes tensile force, one on both sides of each ramp and one in the middle of each caisson, i.e., per 18.30 m, approximately.
Á1-Á7
Indicated Trellex MV 1000X1500 Compound B V Bumpers, or equivalent type.
Trellex MV 500X1500 Compound B Bumpers or other equivalent type, per 18.30 m.
Along the back border of the caissons
  • Two Ö10 pipes made of PVC, incorporated into the superstructure slab concrete, for laying cables
  • Access wells are provided per 18.30 m.
  • Uniform slope 2% to the sea, except for A2-A5 wharf, where there is 1% bilateral slope.

Zoom
Placing of bumpers

   